$548M Wastewater Treatment Plant Improvement Project in New Jersey

Testimonial
$548M Wastewater Treatment Plant Improvement Project in New Jersey

Insured Profile

  • Wastewater treatment plant improvement project in New Jersey
  • OCIP
  • 42-month project

Placement

  • $10M x $25M x P project excess liability policy

Working with Shepherd

After a recent meeting with the broker team to discuss upcoming opportunities, Shepherd received this submission for a 42-month OCIP extension. We provided our initial indication within 4 hours of receiving the submission and turned around our formal proposal within 4 business days to meet the requested deadline; binding the deal on the same day.

‍